CALL 07449 310718River Humber Gas Pipeline Replacement
Project Overview
Duration- 2017- 2021
Some of the duties completed:
Site setup
STP & Filter press installation
TBM assembly and launch
Booster pump installation
All areas of labour covered (up to 35 people on site at one time)
Compressed air works
Supervision of workshop and maintenance
Tunnel repair works and resin injection
Site demobilisation
Snowdonia (VIP)
Project Overview
Duration- November 2023 – 2026 (predicted)
Some of the duties completed:
Site setup
Installation of STP, filter press, workshop
London Power Tunnels (LPT1)
Project Overview
Duration- November- December 2023
Some of the duties completed:
Supply and design assistance of tunnel brackets and associated steel work
All steel designed, fabricated, galvanised and delivered within a rapid turnaround period
All works completed on time and passed back to client
London Power Tunnels (LPT2)
Project Overview
Duration- 2021- 2024
Some of the duties completed:
Site setup
TBM assembly and launch
Electrical and mechanical labour covered (up to 20 people on site at one time)
Supervision of workshop and maintenance
Fixed crossings installation and removal
Site demobilisation
P3 & P5 works
Kit out of tunnel cables, brackets and monorail achieving the best production throughout the job to date
Design bespoke materials to aid the works